Construction Updates
Each year, the Village of Westmont coordinates, schedules, and performs a number of construction updates that improve our community's infrastructure for our residents and businesses.  Also, the County and State perform various construction projects that may impact our community.  This page has been designed to provide information regarding construction projects that will impact the Village of Westmont in the upcoming year.


CBD Alley Reconstruction Project SecF
Contract completion date:  August 2017

Location:  
Central Business District (CBD) Alley bounded by Cass & Linden from Chicago & Norfolk

Description:  
Reconstruction of the deteriorated asphalt alley with decorative pervious brick pavers and pervious concrete base for structural stability.  Project also includes storm sewer installation along the alley.

The project has been successfully let with R.W. Dunteman as the qualified low bidder.  We anticipate construction to begin in early June 2017 (after Manning School lets out for summer break).


Construction Activities Ongoing: (Updated 05/12/2017)

Week ending 05/12/2017
Pre-construction meeting was held on 04/28/2017.  The Village also held an Open House Meeting for Businesses and Residents to attend and view project details on 05/11/2017.  The project is scheduled to begin on Wednesday, June 7th (the day after Manning School lets out for summer break).  Utility locates indicate NiCor has utilities that are in conflict with the proposed alley improvements.  NiCor will begin relocation work in the next couple of weeks.



East Richmond Water Main Replacement Project (Phase 2)

Contract completion date:  August 2017

Location:  
East Richmond between Cass and Wilmette

Description:  
Replacement of existing 4" and 6" cast iron watermain with new 3,000 LF of 8" PVC Watermain.  Project also includes installation of new fire hydrants, water valve vaults, sidewalk improvements, and resurfacing of Richmond Street from Cass Avenue to Richmond Avenue.

The project has been successfully let with R.W. Dunteman as the qualified low bidder.  We anticipate construction to begin in early June 2017 (after Holy Trinity School lets out for summer break).


Construction Activities Ongoing: (NO UPDATES AT THIS TIME)




Naperville-Warwick Storm Sewer Improvement Project
Contract completion date:  November 2017

Location:  
Along north Warwick between Melrose and Norfolk

Description:  
Installation of 1,200 LF of 36" storm sewer from Warwick & Melrose southerly to Warwick & Norfolk.  Project also includes watermain replacement, sanitary sewer relocation, street resurfacing, sidewalk improvements, and other related work.

The project has been successfully let with Elanar Construction as the qualified low bidder.  We anticipate construction to begin in early May 2017.


Construction Activities Ongoing: (Updated 05/12/2017)

Week ending 05/12/2017
Pre-construction meeting was held on 04/25/2017.  Preliminary construction work has begun this week with utility locates.  We anticipate material and equipment mobilization the upcoming week.





Richmond Avenue Resurfacing Project (Partner with the Village of Clarendon Hills)
Contract completion date:  November 2017

Location:  
Along north Richmond between Chicago Avenue and Ogden Avenue

Description:  
The Village has partnered with the Village of Clarendon Hills to perform maintenance work along Richmond Avenue.  Work will consist of resurfacing of the roadway, sidewalk improvements, installation of the concrete shoulder, and other related work.


Construction Activities Ongoing: (Updated 05/12/2017)

Week ending 05/12/2017
Contractor has started layout and began performing driveway removals.






=========================================
For more information regarding Westmont Public Works projects, please contact Noriel Noriega at 630-981-6295.